Operator
Thank you for standing by, and welcome to the Boss Energy Investor Conference Call June Quarter 2. [Operator Instructions] I would now like to hand the conference over to Mr. Matt Dusci, Managing Director and Chief Executive Officer. Please go ahead.
Matthew Dusci
MD, CEO & Director
Thanks, Val. Good morning, everyone. Thanks for joining the Boss Energy June quarterly conference call. Joining me on the call is Justin Laird, our CFO. I’ll provide an overview of the quarter and the full year results. And at the end of the call, we’ll be happy to take questions.
Turning to Slide 2. The June quarter was a strong finish to FY ’26. We delivered our revised production and cost guidance. We continue to strengthen our financial position, and we further established the operating platform required to support growth. Honeymoon production recovered strongly from the rain affected March quarter with drum production of 362,000 GBP, up 79% from the prior quarter. For the full year, production was 1.41 million GBP of uranium, up 61% on FY ’25 and within our revised guidance range. Cost performance was also within revised guidance with full year C1 costs of $39 per GBP and all-in sustaining cost of $61 per GBP.
During the quarter, the company completed and commissioned key operating infrastructure, including NIM 6 columns 4 and 5, the associated pumping systems and the East